Foundational Asset Condition Assessment Project progress update - April

8 April 2025

The survey work for Murray Irrigation's Foundational Asset Condition Assessment Project (FACAP) is progressing steadily across the network, with the Ground Control Survey now 100% complete.
 
The 
Aerial Survey work is moving along steadily and is now 50% captured.

The following image displays the areas completed (in blue). The team is now working in the East around Deniliquin, Tocumwal, Jerilderie and Berrigan. 

The Bathymetric Survey is also progressing and is 15% complete. A second crew has now commenced working in the Finley area of the network.

The green line in the image below depicts the completion of the Bathymetric Survey work thus far.

Share this article: